OMAS Successfully Installed a 2.1MWp Solar PV System at Binzagr’s Logistic Center in KAEC

OMAS is pleased to announce the successful installation of a state-of-the-art ground-mounted solar PV system at Binzagr’s Logistics Center. The system has a capacity of 2089.53 kWp and consists of 3,834 JINKO Solar 545 Wp Modules and 18 HUAWEI 100 kW inverters. The project is developed by Three Eight Six Energy and has been completed in November 2023. While waiting from SEC (Saudi Electricity Company). for its commissioning approval, it might be the first ground-mounted solar PV plant under small-scale projects to be approved by SEC.

OMAS is a remarkable EPC contractor in Saudi Arabia due to its competitiveness and its ability to properly prepare and manage all required documentation in SEC’s portal to obtain final approvals for its clients.